A 300 MW expansion to the existing 600 MW Xuwen offshore wind farm in Zhanjiang, China, developed by State Power Investment Corporation (SPIC), has started commercial operation.
The 600 MW Xuwen offshore wind farm was built in two phases consisting of a total of 94 wind turbines. The first of 47 Mingyang’s MySE6.45-180 turbines in the first phase was installed in early 2021 and the entire wind farm was commissioned at the end of 2021.The work on the additional 300 MW started in 2023 with wind turbine installation commencing in the spring of 2024. According to a social media post shared by SPIC, the expansion went into operation on 17 December. More of this article (offshorewind.biz) - link - more like this (wind) - link - more like this (China) - link