born at 321.89 PPM CO2

"Quality is never an accident. It is always the result of intelligent effort." - John Ruskin

Thursday 30 September 2021

(OFF) CHANGHUA 1 & 2A CONSTRUCTION COMPLETED

Singapore-based Keppel Offshore & Marine Ltd (Keppel O&M) has completed the construction of two offshore substations for Ørsted which will be deployed at the 900 MW Greater Changhua 1 & 2a offshore wind farms in Taiwan.

The detailed engineering, procurement, and construction for the two 600 MW unmanned offshore wind farm substations, which comprise the topside modules and jacket foundations, was completed with a perfect safety record, the company said.

The topside modules, which have a combined weight of more than 8000MT, are expected to sail away in late October 2021 to be integrated with the jacket foundations already installed in the Taiwan Strait.

Keppel O&M completed the construction of the jacket foundations earlier in the second quarter of 2021 and will be undertaking the integration work for the offshore substations. When operational, the Greater Changhua 1 & 2a will be Taiwan’s first far shore and large-scale offshore wind project - offshoreWIND.biz - link - Adnan Durakovic - link - more like this - link

No comments:

Post a Comment