MingYang Smart Energy has secured a contract to deliver wind turbines for the Huizhou Gangkou Phase 1 and 2 offshore wind project.

The Chinese turbine manufacturer won the contract from General Nuclear Power Corporation (CGN).

MingYang will deploy 64 MySE6.25-180 wind turbines for the 400MW project.

The first delivery of turbines will begin October 2020 and is expected to complete by August 2021, the company said in a statement.

The Huizhou Gangkou project is located 25km off the coast of Huidong County of Guangdong Province.

CGN plans to connect the Huizhou Gangkou wind farm to the grid in late June 2022 - 